7 available 7 • View allWhat rights do you have in a property if you don't have a signed SPA?


2
Q: Hi,
What happens if a person HAS NOT signed a sale & purchase agreement (SPA) with a developer for a purchase of a property?
Thanks in advance.



Aug 18, 2021
1188
The risk of buying a property almost ready for handover without signing SPA
1
Q: I want to buy an off-plan property but I do NOT want to sign their SPA. The property is almost ready and due for handover in 2-3 months.
The developer is implying that if I pay the full price 100% with no payment plan, it may be possible to bypass signing the SPA, as the property would be paid for 100%.
I don't want to sign the SPA because of a clause inside it which I disagree with on a religious level.
Thank you.

Nov 14, 2021
393
Cancellation of an off-plan property while the SPA is not signed and the project is completed

0
Q: Cancellation of an off-plan property while the SPA is not signed and the project is completed.


Feb 24, 2023
173
The time limit for a developer to pay the 4% registration fee to the DLD




1
Q: Dear Sir/Madam,
Is there a time limit for an off-plan project developer to pay the 4% registration fee to the DLD?
It has been five months since I paid the developer the booking amount and 4% DLD fee, and I have not yet received my Oqood.
Any guidance would be greatly appreciated.
Thank you!





Mar 29, 2023
279
Can I terminate the SPA for an off-plan property and get full refund if I didn't receive the SPA?


0
Q: I booked an off-plan property with a developer in a project in Dubai.
I have paid 10% + 4% DLD. It's been 2 months and still, I don't have SPA. Plus, the above amount is in favor of the developer's account and not escrow.
Please advise if this is normal and what questions I should ask the developer.
Can I withdraw the money from the developer?
Will he be liable to hold any % of my money for cancellation?



Jul 14, 2023
166
Unit registration delays, slow construction. Can I cancel SPA for a refund?




2
Q: Hi,
I purchased a unit in July. I've requested Oqood several times to no avail. They responded that the registration will take time, and the delay is from DLD.
I checked with DLD, and they informed me that no registration application had been made in my name. Additionally, when I purchased the unit, I was promised several things, including Golder Residency, and a flexible payment plan of (70/30), but that was all untrue.
Furthermore, I realized that the developer provided their direct bank account rather than an Escrow account, which raised a red flag for me. The contract stated that the completion time is July 2024, but the construction progress is still under 20% as per the DLD website.
I have the intention to cancel my SPA and request a refund. Will that be doable?





+1
Dec 22, 2023
136
Terminating the SPA of a nearly completed off-plan property in Sharjah



1
Q: Hello,
Terminating the SPA of an off-plan property in Sharjah when the project is almost completed but delayed by 10 months.




Jul 24, 2024
80
Laws & Regulations
2 available 2 • View allLaw No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai 1
This Law establishes interim property register in which sale contracts, off-plan sales, and other off-plan legal dispositions of real property are registered prior to inclusion in the property register maintained by Dubai Land Department.
Aug 14, 2008
4823
Executive Council Resolution No. (6) of 2010 Approving the Implementing Bylaw of Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai 3
This Resolution approves the Implementing Bylaw of Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai.
Feb 14, 2010
5121

Other answers by
313 313 answers •
View allCan the landlord request the tenant to pay the chiller in the middle of the contract? 0
I live in Dubai Marina, and the landlord claimed that according to new Dubai Land regulations, the chiller now has to be paid by the person occupying the apartment.
Even though my contract says that the landlord should pay the chiller, they want to implement this mid-contract.
I understand that the terms upon renewal will be renegotiated, but on what grounds can they implement the change mid-contract?
Does a new DLD regulation precede a tenancy contract? Moreover, I am receiving a disconnection notice from the chiller company due to non-payment.
What can I do if this happens?
Please advise.
Mar 23, 2022
1580
Can I travel with a non-paid telecom bill in the UAE if my visa is canceled? 0
Can I travel with a non-paid telecom bill in the UAE if my visa is canceled?
Feb 16, 2023
724
Does the new property owner have to sign a new contract with the tenant? 0
Hi,
I'm a new landlord of the property which is already rented.
Kindly advise, do we have to sign a new tenancy contract with the tenant for the remaining period? And who will pay the cost of Ejari?
Feb 16, 2023
2558
Cleaner's resignation with 30-day notice in incomplete contract 0
Hello,
Good afternoon!
My friend works as a cleaner for a cleaning company and she now wants to resign with a 30-day notice. However, she has not completed the two-year contract and has only served for 16 months.
Additionally, she has not taken any vacation leave. The sad part is that when she signed the offer letter, she did not receive a copy of it and only signed it.
I would be very grateful if you could let me know if she would have to pay or if her boss has the right to not accept the resignation if the notice period mentioned in the offer letter is more than a month.
Her boss has not provided her with any kind of proof that she can use in the future if anything happens.
Feb 13, 2023
549
The ownership of a code of a web application 0
Hello,
I represent a tech-based marketplace company registered in a Freezone, in the UAE.
This is in regards to the UAE's law regarding the ownership of code when there is no clause mentioned in the agreement. One of our products (web application) is being developed by an agency in the UAE.
While we do have agreements in place, there is no clause regarding ownership of code. In the situation mentioned above, I've heard that the ownership of code either goes to the author or the agency that employed the author. Is this true?
Your assistance and help would be of great help.
Sep 7, 2021
311
Get quotes from lawyers
Find the right lawyer for your legal needs.
Submit your request and get multiple
competitive offers from
qualified lawyers.
Popular Q&A
View all Looking for something else?
Ask for advice from a lawyer