Recovery of money from developer for delay in property handover
I have a property that was supposed to be handed over about three years ago and still isn't. On the SPA, there is no anticipated completion date.
What can I do about this?

Al Nassar Advocates & Legal Consultants
24 Feb 2019, 13:21
Dear Questioner,
Thanks for contacting online.
Even though there is no mentioning about the anticipated completion date, it should be handed over in a reasonable time.
Three years time is a quite unreasonable delay in handing over a property. So you have the right to revoke the deal and ask for your money back along with damages.
You can send a legal notice with your claim and proceed accordingly.
Please feel free to contact me at 0556635526 or WhatsApp me at 0508575526 if you need any further explanation or clarification.
Regards,
Anitha Rajeev
Fixed-fee services
Get quotes from lawyers
Find the right lawyer for your legal needs.
Submit your request and get multiple
competitive offers from
qualified lawyers.
Popular Q&A
View all Looking for something else?
Ask for advice from a lawyer