7 available 7 • View allPossibility to terminate the SPA and claim refund for handover delay

1
Q: Hi,
I purchased an off-plan property in Dubai that had an estimated completion date of August 31, 2020.
I received an email that due to a delay, my completion date has been pushed forward to April 30, 2022. The email they sent for the delay did not say what was the reason for the delay.
Since the developer has violated the SPA by delaying the project past 12 months of the completion date, can I request that the contract be cancelled and get what I have paid back?
Do you believe that the developer could utilize Covid-19 as Force Majeure as a reason for not following the contract?
Regards


Jul 4, 2020
516
Delayed property projects and the right to exit the SPA
3
Q: Delay in property completion and need for cancellation and exit from SPA
Hello All,
I booked for an off-plan property in Downtown Dubai by a leading builder. The completion date was June 2018. However, the property was not completed in June of 2018.
I received a note in April 2018 citing the new completion date would be Dec 2019.
Since the completion date is well over the stipulated grace period in SPA, I had requested the builder for a friendly settlement by cancelling the SPA and refunding the money as per the default by vendor clauses in the SPA.
This has been refuted by the builder and repeatedly says that they cannot cancel the SPA and neither can they refund the money. What are the options available?

Mar 21, 2019
1846
What legal action can I take for delay in property handover?
4
Q: I purchased an apartment in 2017 with a completion date of Q4-2018. Till now, the construction is not complete. And based on the construction update, it will not complete in 2020.
As per the agreement I already paid 50% of the amount and rest 50% is due on completion. As per the Default and Termination clause of the SPA, I sent the notice for termination on 5th Jan 2019.
This clause clearly states that "If the seller has not served the completion notice within a period of 12 months from the anticipated completion date (unless the delay is caused by force majeure) and the purchaser has fulfilled all of the purchaser obligations under this agreement, the purchaser shall be entitled to send a written notice to the seller requiring the seller to complete the building works within 90 working days of receipt of the purchaser's written notice.
That time has elapsed and now I have to send the second notice as the remedial period of 20 days is also coming to an end.
Please advise on the plan forward.

Jun 14, 2020
2334
Claiming penalty for delay in property handover or termination and refund

0
Q: I have purchased a property in a Dubai project and as per my agreement, they are supposed to give me possession by the second quarter of 2019.
However, they have still not given possession and when I ask for the delay compensation of 4%, they are not responding to that.
As per Dubai Real Estate Law, can I cancel the contract?
I am no more interested in continuing with these guys. If I file a case in the court, will the court ask them to pay the delayed charges as well as the legal expenses?
Please advise


Jul 14, 2020
1348
Termination of SPA and claiming refund after project cancellation
1
Q: I had Invested in an upcoming residential project in June 2018 & paid 20% of the total property value.
But there has not been any progress in their construction & also checked with Dubai Land Department & the developer as well for the status, and learnt that it is probably under cancellation.
I requested via email to the developer for a refund but they have instead suggested me to opt for an ongoing project or a ready to move in property.
But I do not intend to proceed & want my money back at the earliest possible. I have the SPA & proof of payment made i.e. Invoice as well.

Aug 16, 2020
632
Termination of property SPA and claiming refund for handover delay



2
Q: I purchased an off-plan property studio in Mar' 2018 from a well-reputed builder in Dubai. The anticipated handover date was March' 2020.
In Aug 2019, I received notice that there is a fire incident at the site. Same month Aug' 2019 I have cross-checked the project status on the Dubai Land Department website which shows only 23% of work has been completed.
It was clearly understood that the project was running late & they were never in a position to complete on-time March' 2020 even if the fire incident would not have happened.
In the month of handover Mar' 2020, we have received that due to force majeure the handover is delayed & the remaining monthly instalments are paused & will be taken on completion, paid 50% till now.
As I understand from my contract, delivery can be pushed by up to 12 months, however, there is no mention of actual delay that can be taken on a note of force majeure.
What are my options with the developer? My preference would be to terminate the contract and get my money back.




Aug 27, 2020
454
Termination of an off-plan property SPA and getting a refund
1
Q: Hello,
My father had purchased an off-plan hotel room (rental-pool) in Dubai. He paid the deposit and all fees and has been paying all installments on schedule towards the developer's escrow account. However, the project's ACD was on June 19, with the six-month extension, Dec '19.
He stopped paying the installments after the extension period (paid around %65) on the grounds that the project is yet not running and not generating him any revenue. According to the DLD, the project reached 100% completion on October 20.
He asked the developer to cancel the SPA after the extension period, but they kept stalling and saying it is not possible. Moreover, they provided us with different dates for the ADC. The SPA says June 19 while the Property Reservation Agreement says Dec 19.
Due to financial constraints, he cannot continue with further payments. What is the possibility to cancel the SPA through the DLD or Real Estate Courts in Dubai?

Nov 19, 2021
279
Legal blog
1 available 1 • View allنظرة في الطعن 4 لسنة 2023 قرارات الهيئة العامة لمحكمة تمييز دبي 32
بتاريخ 24/10/2023، صدر قرار الهيئة العامة لمحكمة تمييز دبي في الطعن 4 لسنة 2023 مرسياً مبدأً جديداً مفاده أن الأصل في الناس هو الإعسار وأن اليسار عارض، وأنه يتعين -تبعاً لذلك- على طالب التنفيذ أن يثبت يسار خصمه المنفذ ضده أو تهريبه لأمواله كي يستصدر أمراً بضبطه وإحضاره ثم حبسه لإكراهه بدنياً على السداد. وكما هو متوقع، أحدث هذا القرار ردود فعل كثيرة ومتنوعة، سيما وأنه قرار نوعي يقلب كثيراً من الأوضاع المعتادة رأساً على عقب ويغير من الحالة الاجتماعية السائدة الشيء الكثير.
Nov 20, 2023
1500
Laws & Regulations
3 available 3 • View allLaw No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai 1
This Law establishes interim property register in which sale contracts, off-plan sales, and other off-plan legal dispositions of real property are registered prior to inclusion in the property register maintained by Dubai Land Department.
Aug 14, 2008
4822
Law No. (9) of 2009 Amending Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai 2
The provisions of this Law supersede articles (2) and (11) of Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai.
Apr 12, 2009
3113
Executive Council Resolution No. (6) of 2010 Approving the Implementing Bylaw of Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai 3
This Resolution approves the Implementing Bylaw of Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai.
Feb 14, 2010
5121

Premium
Other answers by
240 240 answers •
View allHow to change the lease contract for an entity that changed from sole establishment to LLC? 0
Good morning.
Kindly help me out with the below query:
If a sole establishment is converted into an LLC, what would happen to the existing Lease Agreement with the Sole Establishment as the tenant?
Thank you.
Aug 23, 2024
116
Bank filed a civil case over a loan: Better to settle with the bank or in court? 0
Good day, Sir,
I have received a message from the Dubai Court stating that a bank has filed a civil case against me. The loan has been pending since February 2019.
I cleared the cheque bounce case earlier with a court fine in 2019. I am looking forward to a minimum settlement plan with the bank. The outstanding amount was around 70,000 AED, and now the message is for 115,000 AED.
What will be the best way for me to proceed: approaching the bank or dealing with it in court?
Best regards,
Jul 7, 2024
523
Is it legal for my employer to withhold my salary until I leave the country or change status? 0
Hello,
I have given my notice, and my last day is July 24, but the employer is refusing to pay my salary; even the salary for June. Is this even legal?
He claims I'll get everything at once, which is after leaving the country or changing status.
Jul 2, 2024
536
Demanding that an employee pay for visa charges a year after resigning 0
Dear Lawyers,
I worked at a bakeshop here in Dubai. I resigned exactly one year ago. Now they want me to pay for visa charges, as stated in the offer letter.
If I cannot pay for the charges, my employer will claim financial loss due to the damages, estimated to be at least 7,000 AED.
What should I do about this? My monthly salary is only 2,800 AED.
Jul 1, 2024
117
Is an employee eligible for maternity leave in the first three months of pregnancy? 0
Dear Lawyers,
Is an employee eligible for maternity leave in the first three months of pregnancy?
If an employee takes sick leave in the first three months of pregnancy, can it be considered normal sick leave or maternity leave?
Jul 1, 2024
172

Other answers by
108 108 answers •
View allCan you enter Dubai if you leave a GCC country with possible civil and criminal cases? 0
Hi Hayyan,
In 2014 I had been to Qatar on a "Work-Business" visa valid for 30 days. Before my visa expiration, I fled from Qatar back to India without informing the sponsor or office management.
After I returned to India, I received an email from HR stating that the Qatari sponsor has filed an absconding case, a civil case, and a criminal case against me with the Ministry of Interior in Qatar.
Now my question is, can I travel to Dubai on a work visa?
Will there be any issue entering Dubai assuming that the Qatari sponsor has filed the said cases against me?
Awaiting your response,
H.
Currently staying in India.
Mar 8, 2022
421
Help with drafting service provider agreement for marketplace tech startup 0
We are a tech startup creating the first auto/car service and repair marketplace.
As a marketplace, we only facilitate listing and booking the services while the service providers (the workshops) are the service providers and are responsible to deliver and carry the selected /booked job.
We need to draft a marketplace supplier/service provider agreement between us and the workshops outlining the responsibilities and liabilities of both sides.
I would like to work with a law firm that has previous experience in drafting such marketplace-related agreements.
Dec 7, 2021
379
Drafting an agreement between an auto service marketplace and service providers 0
Hi Mohammed,
We are a tech startup creating an auto service and repair marketplace. As a marketplace, we only facilitate listing and booking the services while the service providers (the workshops) are the service providers and are responsible to deliver and carry the selected/booked job.
We need to draft a marketplace supplier/service provider agreement between us and the workshops outlining the responsibilities and liabilities of both sides. I would like to work with a law firm that has previous experience in drafting such marketplace-related agreements.
Is this something you can work on and have previous experience in?
Dec 6, 2021
356
Legal assistance in preparing T&Cs and privacy policy for startups 0
Hi,
I am starting a website that connects freelancers to media professionals and individuals. It will be a marketplace sort of platform.
Where can I find a legal advisor to help with the terms and conditions and privacy policy for startups?
Thank you for your reply in advance.
N.
Sep 20, 2021
159
Legal requirements for starting a business by a minor 0
Legal requirements for starting a business by a minor in the UAE
I am currently 16 and I’m an Emirati national. I am willing to start my own e-commerce business.
Is it possible to get an e-commerce license even if I am a minor?
Jul 12, 2021
1244

Other answers by
71 71 answers •
View allThe tenant's right to refuse visits of potential buyers without prior consent 0
I am the owner and have legally notified my tenant regarding my intention to sell and have given her first right of refusal.
But she is not signing nor allowing me access to arrange visits for other interested clients.
What are my rights / legal steps to force a viewing
Feb 17, 2021
9710
The developer refuses to pay the money back after delivery delay due to force majeure 0
I am seeking legal advice to terminate the contract due to a delay in the project for a period of 16 months only.
The following is the details of the project as per SPA and some givens:
- 30% paid in installments (on time, no delay in payment).
- 70% to be Paid on Handing Over.
- Expected Handing over date: 1st April 2019.
- Longstop date of Handing over: 1st April 2020.
- Actual date of delivery announced by developer: 10th August 2020.
- Notification sent to the developer by myself to terminate the SPA and return the 30% paid amount.
- Developer responded that the notification is rejected as the delay is due to force majeure (Covid-19 Pandemic).
Question:
Do I have a winning case if I filed to court to return the paid amount?
Feb 17, 2021
619
Overstaying because a family member is tested positive for COVID 0
Our residence visa grace period expires soon. Because a family member is positive for Covid-19 and he is in-home quarantine, we are unable to fly within the grace time. What should we do?
Will we be fined?
Please guide!
Feb 17, 2021
771
Cancellation of a property purchase and refund for over-delay in handover 0
Hello
I am contacting you from London. I have purchased a property in Dubai in a project in 2005. We purchased two apartments and today we have not received anything yet.
This construction project is still going on and the developer has changed many times. Another company now runs the project, and whenever I contact them they say it's going to be ready in the next 3-months or 6-months.
It keeps postponing work are currently at standstill. I have contacted them then and the same they're waiting for more information from the Dubai authorities.
Every time there's a different story, and we get delayed. It's now been 16 to 17 years since we have invested in this and I would like to put a stop to this now, possibly get a refund and compensation.
Could you please help me by advising me what my situation can be?
Feb 1, 2021
820
Can a father claim the custody of daughter when the mother marries unfit person? 0
My wife and I got divorced 3 months ago, she has custody of our 6-month old daughter.
She wants to remarry but I disagree with the person she wants to remarry as he has a history of violence and abuse.
Can I have the custody agreement revoked?
Mar 26, 2022
715
Get quotes from lawyers
Find the right lawyer for your legal needs.
Submit your request and get multiple
competitive offers from
qualified lawyers.
Popular Q&A
View all Looking for something else?
Ask for advice from a lawyer