أسئلة وأجوبة
A claim to terminate SPA and claim refund for delay in handover
Dear Lawyers,
I need your advice about my situation below.
In 2018, I purchased a unit from a developer which they wrote on the reservation form that completion date is Q2-2019.
Therefore, I paid 24% including Oqood fees (approximately AED 109000) of the amount of (AED 534430) at booking. Then I paid 50% of the amount as mentioned in the reservation on time.
However, when I received the SPA, they changed the completion date to Q1-2020 which I signed as well. Now, the building progress is 45% and they mentioned that completion would be in Q2-2021.
Until this time, I did not receive the DLD registration and I need to know what is the best solution in this case. I have asked them many times about it but they keep ignoring me.
I do not think they will deliver even on the time they mentioned.
Is their a possibility to get my money back, or should I wait until Q2-2021 as they mentioned?
I appreciate your help.
Best regards

عزيزي العميل،
طاب يومك.
نحتاج إلى الاطلاع على اتفاقية البيع والشراء للتحقق من تاريخ الانتهاء.
إذا كان مذكور بوضوح أن تاريخ الانتهاء المقرر هو عام 2021، فإنه يجب عليك الانتظار حتى حلول تاريخ الانتهاء وإكمال فترة الإشعار حتى تتمكن من اتخاذ إجراء ضدهم.
ومع ذلك، يحق لك رفع قضية تعويض ضدهم بسبب تأخير تسليم المشروع.
لا تتردد في التواصل معنا عن طريق الهاتف أو عبر البريد الإلكتروني لمزيد من المساعدة.
شكرًا لك.