أسئلة وأجوبة

اسأل محاميًا
جميع المدن, الإمارات العربية المتحدة

Possibility to terminate the SPA and claim refund for handover delay

Hi,

I purchased an off-plan property in Dubai that had an estimated completion date of August 31, 2020.

I received an email that due to a delay, my completion date has been pushed forward to April 30, 2022. The email they sent for the delay did not say what was the reason for the delay.

Since the developer has violated the SPA by delaying the project past 12 months of the completion date, can I request that the contract be cancelled and get what I have paid back?

Do you believe that the developer could utilize Covid-19 as Force Majeure as a reason for not following the contract?

Regards

بروكنسلت للمحاماة والاستشارات القانونية
دردشة
توظيف
اجتماع
4 Jul 2020, 06:50

نحتاج إلى الاطلاع على أحكام اتفاقية البيع والشراء.

إذا كانت اتفاقية البيع والشراء تسمح بتمديد فترة الإنجاز، عندئذٍ لن يكون هناك انتهاك للاتفاقية.

لا تتردد في التواصل معنا عن طريق الهاتف أو عبر البريد الإلكتروني.

أسبتيف للاستشارات القانونية
دردشة
توظيف
اجتماع
4 Jul 2020, 07:11

عزيزي السائل،

في العادة، يُسمح للمطورين العقاريين بتمديد 12 شهرًا من تاريخ التسليم المُتوقع.

لكننا نحتاج إلى الاطلاع على اتفاقية البيع والشراء الموقّعة بشكل متبادل لتقديم المساعدة لك بشكلٍ صحيح.

إذا لزم الأمر، يرجى التواصل معنا عن طريق الهاتف لإجراء مناقشة تفصيلية أو مراسلتنا عبر البريد الإلكتروني للحصول على مزيد من المساعدة.

خدمات برسوم ثابتة
2 2 خدمات متاحة •  عرض الجميع
احصل على عروض أسعار من محامين
ابحث عن المحامي المناسب لاحتياجاتك القانونية. أرسل طلبك واحصل على عدة عروض تنافسية من محامين مؤهلين.
هل تبحث عن شيء آخر؟
اطلب استشارة من محامٍ
الخدمة مجانية وهويتك مخفاة
لا حاجة للتسجيل
اسأل محاميًا