I have 2 properties bought off-plan. Both are overdue. Both are above 90% completed & approximately 6-9 months overdue.
I lost my job due to COVID-19 & can no longer fulfil my financial obligations. The properties are with [--------] & [-------].
Is it possible to win a case, cancel the SPA & get my money back?

Premium
Abdelaziz Al Zaabi Advocates & Legal Consultants
22 Jun 2020, 21:40
Dear Questioner,
Regarding for COVID-19, the federal government and the local law in Dubai made a new decision which considered that COVID-19 is an act of god which allows terminating all contracts in general.
So if you prove to the court that you lost your job, you can terminate the contract. But you need to search for an additional reason to add in your case to make it stronger.
Regards
Mohmed Gadalla
Fixed-fee services
Get quotes from lawyers
Find the right lawyer for your legal needs.
Submit your request and get multiple
competitive offers from
qualified lawyers.
Popular Q&A
View all Looking for something else?
Ask for advice from a lawyer