Default in fulfilling obligations under off-plan property purchase

I bought an off-plan property In Abu Dhabi and have paid some percentage as part of the flexible payment program for the down payment.

However, no sale and purchase agreement has been provided to be signed by both parties.

Construction did not commence and recently, the entire project has been moved to another developer.

I have been contacted by the new developer and was told the project construction start date is indefinite.

Based on this, can I get a refund as I only have the reservation agreement and no contract has been signed, plus the project has not started which will definitely not be completed in time (even with a six months delay allowance)?

أوس ليجال كونسولتانسي
دردشة
توظيف
اجتماع
17 Jul 2018, 06:34

سيدي العزيز،

أتمنى أن تكون بخير.

فيما يتعلق بسؤالك، يرجى العلم بأنني أحتاج المعلومات / المستندات المبدئية المذكورة أدناه قبل تقديم المشورة لك في موضوع العقار الخاص بك:

1. اتفاقية الحجز.

2. المبلغ الذي تم دفعه إلى الآن.

3. أي رسائل بريد إلكتروني تطلب فيها اتفاقية البيع والشراء وتبين التأخير في البناء.

عند استلام المستندات والمعلومات المذكورة أعلاه، سنقوم بمراجعة الأمر، وسوف نقدم لك رأينا في كيفية المضي قدمًا في المطالبة باسترداد المبلغ بأكمله.

لدواعي الخصوصية، يمكنك إرسال المستندات والمعلومات المطلوبة على البريد الإلكتروني info@awsuwaidi-advocates.com، أو يمكنك الاتصال بنا على 045547635.

نتطلع إلى استلام رسالتك.

مع التحية،

أوس م. يونس

خدمات برسوم ثابتة
3 3 خدمات متاحة •  عرض الجميع
احصل على عروض أسعار من محامين