Can you sue the developer after failing to hand over property beyond grace period?
Dear, good day,
The developer failed to hand over the project by Mar 2020 as per the SPA. Installments were paid on time, he is in dispute with his construction contractor.
He wanted to change him since there was a fire at the construction site, however, the authorities granted permission to resume construction after the investigation is finished last year.
The developer still to this date failing to terminate the defaulted old contractor and appoint a new construction contractor which is causing a delay.
I have requested termination of SPA and claimed a refund but was declined. The project construction is still around 30% since more than 15 months where it should be 100% back in Mar-2020.
There is a clause in SPA to grant 1 year and 90 days (remedy period), I have sent a written notice to claim a refund as per the contractual clause and time frame.
Could you please advise what are the steps and chances to push the developer to refund full amounts? Should I start with RERA first?
Thanks in advance.

عزيزي السائل،
يجب علينا الاطلاع على اتفاقية البيع والشراء الموقّعة بشكل متبادل لتقديم المساعدة لك بطريقة صحيحة.
إذا تخلف المطور العقاري عن الوفاء بالتزاماته الأساسية عن طريق التأخير في تسليم العقار، فإنه بالتأكيد يحق لك إلغاء اتفاقية البيع والشراء الموقّعة بشكل متبادل وطلب استرداد أموالك التي دفعتها حتى الآن بالكامل، بالإضافة إلى تعويض عن التأخير.
يرجى التواصل معنا مباشرةً عن طريق الهاتف أو عبر البريد الإلكتروني لمناقشة الأمر بالتفصيل.

مرحبًا،
ردًا على استفسارك، يرجى ملاحظة أنه يمكنك البدء بتقديم شكوى إلى مؤسسة التنظيم العقاري، وإذا لم تتخذ المؤسسة أي إجراء، فإنه يمكنك رفع قضية تعويض عن التأخير.
يرجى التواصل معنا عن طريق الهاتف أو عبر البريد الإلكتروني.