Refund of an off-plan property payments for delay in delivery
Salam,
Hope you are very well.
I am writing this email to understand the current law for off-plan properties in Dubai.
I started an agreement with a developer in Dubai in 2016 4th quarter. The developer promised to deliver the project by June 2019. Currently, the project is only 23% completed.
When I saw the project is being delayed, my payments were delayed too I paid around 40% of the unit price. Now I received an email/letter from the developer on the final Legal Notice, or they would cancel my unit.
Does the developer have such rights even though its a big delay from there end?
If they cancel my unit, what % of my total paid money will I be refunded from them?
I would appreciate your detailed and kind response in this matter, please.
Thanks

مرحبًا،
تخضع جميع اتفاقيات البيع والشراء هذه إلى هيئة التظيم العقاري في دبي بالإمارات، وهي تغطي حقوق المشتري في حالة التأخير وكذلك المطورين في حالة حدوث تأخير في المدفوعات من المشترين.
للحصول على رد مفصل، سيتعين علينا التحقق من الاتفاقيات التي وقعت عليها مع المطور بالإضافة إلى سجلات السداد.